Downtown Condo | Tribute – Blog http://mytributeblog.ca Your Tribute Community News Fri, 27 Jul 2018 15:03:42 +0000 en-CA hourly 1 https://wordpress.org/?v=4.8.8 http://mytributeblog.ca/wp-content/uploads/2017/06/cropped-tri_logo-01-32x32.png Downtown Condo | Tribute – Blog http://mytributeblog.ca 32 32 Stanley Condos – Fall Construction Update http://mytributeblog.ca/?p=639 Thu, 02 Nov 2017 19:02:45 +0000 http://mytributeblog.ca/?p=639

Stanley Fall Construction Update

The summer was good to our team at Stanley as great progress has been made thus far.  The crane was erected in mid August and shoring was completed as of September 2017.  Forming began in late September 2017 and excavation was fully completed by October 2017.

Currently, the slab on grade is 50% complete and our team will be pouring the first portion of the P4 level this month!  Our team's target is to fully complete the underground structure by early 2018.  This highly anticipated project is 90% sold and located in the heart of downtown with the convenience of transit, shopping, and entertainment within walking distance!  

Crane base preparation.
September 2017
October 2017 - shared by @privait 
Preparing for p4 suspended slab - November 2017
 
 
For more information on available suites for sale please contact our sales office.
T: 416.546.1502

[email protected]

475 Yonge St, Toronto, ON. M4Y 1X7

 

Did this information help you? Share with us on Twitter, Facebook, or Instagram!
Don't forget to hashtag #MyTributeBlog!
]]>
Stanley – Construction Update Summer 2017 http://mytributeblog.ca/?p=178 Fri, 16 Jun 2017 14:41:45 +0000 http://mytributeblog.ca/?p=178

Stanley – Construction Update Summer 2017

This highly anticipated condominium building is well underway.

Located at Church and Carlton, this Downtown Toronto project is located in the heart of the city.

 

 

Excavation and tie backs are in progress and currently completed up to parking level 3 of 5.

Our Tribute team is working hard and using the beautiful summer weather to their advantage!

We are expected to be at footings by late July.  Crane installation is also targeted for end of July.